Electricity Forum Intelligent Power Today Magazine Arc Flash Clothing

T&D Companies


FERC Conference Highlights Challenges in Resource Adequacy

The Federal Energy Regulatory Commission (FERC) recently hosted the Co-Located Load Conference, a significant event that focused on resource adequacy, energy reliability, and the challenges of ensuring sufficient electricity supply amidst changing grid dynamics. As the energy landscape continues to...

Current Trends in Transmission and Distribution

Sargent & Lundy has provided comprehensive engineering, development, permitting, high-level consulting, construction management, and commissioning services for electric power generation and power delivery projects worldwide—approximately 2,000 clients in nearly 100 countries—since...

Why Net-Zero is Cheaper for the UK

The United Kingdom has set an ambitious target to achieve net-zero greenhouse gas emissions by 2050. This goal necessitates a comprehensive transformation of various sectors, including energy, transportation, and agriculture. While the environmental imperatives are clear, there is growing evidence...


Power Transformer Failures

Electric utilities maximize utilization of their assets, while maintaining reliability. Power transformers are typically reliable, but have been known to fail suddenly and/or prematurely. Transformer failures are both costly and can leave customers dissatisfied, harming the reputation of a utility....

Acutran Transformers: Built to Military Precision

Acutran is a veteran-owned custom designer and manufacturer of low- and medium-voltage dry-type transformers from 10VA to 3000kVA with voltages up to 25000V, inductors and reactors, and related components and services.The company was founded in 1983 and is now owned by Mike Evans, who is also the...

T&D Companies

transformer repair

Radiator Fin(s) Leak Repair

Radiator fins are notorious for leaking at various locations. One of which is where the fins are attached (welded) to the horizontal bottom-run header. Measurements are taken so a weir box can be installed to cover the fin(s) that are leaking. It is preferred the weir box will cover above the leaking area about 6".
This 6” cover will allow for urethane (poured into weir box) to adhere to the drier part of the fin(s) to assist with the sealing process. After pour, the technician will mark the outside of the weir box at the location(s) where the original leak was. This incase further work may be required for a better seal. After the urethane is poured and let to cure (usually overnight) the job is inspected to determined seal effectiveness. In the event we still have some leakage; whether the following day or later, an additional procedure may be performed. If leaking, the weir box is fabricated out of 11ga galvanized sheet metal which is thick enough for completing a 1/16" NPT. The technician will decide where (usually where it's been marked) and how many 1/16" D&T’s (drill & taps) are required. Once additional d&t's are completed, injection valves installed, then a special 2-part sealant (must be approved from a dielectric and DGA standpoint) will be injected. The thought is: now that there is cured urethane above the original leak(s) and we have marked the weir box for injecting close to that spot, we have created a bridging barrier for our sealant to back up against (so as not to extrude out the top of the weir box).

T&D Companies Articles