Electricity Forum Intelligent Power Today Magazine Arc Flash Clothing

T&D Companies


FERC Rejects PJM Transmission Planning Change

The Federal Energy Regulatory Commission (FERC) has rejected a proposal from PJM Interconnection, one of the United States' largest regional transmission organizations, to alter its transmission planning protocol. The decision represents a significant victory for state regulators who had expressed...

Why Net-Zero is Cheaper for the UK

The United Kingdom has set an ambitious target to achieve net-zero greenhouse gas emissions by 2050. This goal necessitates a comprehensive transformation of various sectors, including energy, transportation, and agriculture. While the environmental imperatives are clear, there is growing evidence...

The SorbWeb™ Plus DRH4 Synergy

If you have oil-filled transformers, the law requires you to have a spill prevention plan in place, up to and including a secondary containment system to protect the environment and prevent oil from reaching navigable waters. Albarrie and Voltra Technology have partnered up to provide the power...

Restoring Power: The Mobile Solution

Power has weaved its way into nearly every intrinsic detail of our lives. It has become an afterthought during the course of the day and indeed, it is a staple in our way of life.In July of 2019, in the heart of the nation’s capital, a Potomac Electric Power Company (PEPCO) substation in...

Current Trends in Transmission and Distribution

Sargent & Lundy has provided comprehensive engineering, development, permitting, high-level consulting, construction management, and commissioning services for electric power generation and power delivery projects worldwide—approximately 2,000 clients in nearly 100 countries—since...

RMS Energy Responds to the Changing Engineering Needs of Customers

Today’s electrical infrastructure in the United States might have been viewed as a work of science fiction when the first commercial power grid was conceived and built in New York’s lower Manhattan in the 1880s. But it didn’t take long for fiction to become fact. Thomas...

T&D Companies

transformer repair

Radiator Fin(s) Leak Repair

Radiator fins are notorious for leaking at various locations. One of which is where the fins are attached (welded) to the horizontal bottom-run header. Measurements are taken so a weir box can be installed to cover the fin(s) that are leaking. It is preferred the weir box will cover above the leaking area about 6".
This 6” cover will allow for urethane (poured into weir box) to adhere to the drier part of the fin(s) to assist with the sealing process. After pour, the technician will mark the outside of the weir box at the location(s) where the original leak was. This incase further work may be required for a better seal. After the urethane is poured and let to cure (usually overnight) the job is inspected to determined seal effectiveness. In the event we still have some leakage; whether the following day or later, an additional procedure may be performed. If leaking, the weir box is fabricated out of 11ga galvanized sheet metal which is thick enough for completing a 1/16" NPT. The technician will decide where (usually where it's been marked) and how many 1/16" D&T’s (drill & taps) are required. Once additional d&t's are completed, injection valves installed, then a special 2-part sealant (must be approved from a dielectric and DGA standpoint) will be injected. The thought is: now that there is cured urethane above the original leak(s) and we have marked the weir box for injecting close to that spot, we have created a bridging barrier for our sealant to back up against (so as not to extrude out the top of the weir box).

T&D Companies Articles