Electricity Forum Intelligent Power Today Magazine Arc Flash Clothing

Electrical Transformers


Renewable Insulation Liquids for Transformers

Turning electrical assets into green machines BY RONNY FRITSCHE & GEORG PUKEL, Siemens AG Transformers are one of the most important components of energy grid systems. They enable the efficient transport of electric energy from the location where the energy is generated to the location where...

Transformer Software & Technologies


Smart Transformers

Maximizing continuous and reliable power output, extending the life of a power transformer, and reducing maintenance costs are just a few of the benefits motivating electric utilities to move toward buying a “smart transformer”, electrical equipment integrated with Smart Grid-enabling software...

Transformer Monitoring


Transformer Protection


Protection of Electrical Power Transformers

INTRODUCTIONIn most large electrical systems, generators and power transformers are the two most expensive pieces of equipment. In addition to the capital cost of purchase, these two key devices are also the most critical to continuous and reliable operation of the system.Consider, for example, the...

Dielectric Fluids


The End of the Road for Transmission Incentives

In a significant shift, the Federal Energy Regulatory Commission (FERC) has decided to abandon its transmission incentives policy, particularly the construction work in progress (CWIP) incentives. This decision marks a pivotal change in how transmission projects are financed and regulated,...

Utility Transformers


FERC Approves Interconnection for Talen Energy, Amazon Data Center

In a significant move that underscores the growing demand for reliable and sustainable energy to power the expanding digital infrastructure, the Federal Energy Regulatory Commission (FERC) has approved an interconnection agreement between Talen Energy, Amazon Web Services (AWS), and Exelon. This...

Power Transformers

transformer repair

Radiator Fin(s) Leak Repair

Radiator fins are notorious for leaking at various locations. One of which is where the fins are attached (welded) to the horizontal bottom-run header. Measurements are taken so a weir box can be installed to cover the fin(s) that are leaking. It is preferred the weir box will cover above the leaking area about 6".
This 6” cover will allow for urethane (poured into weir box) to adhere to the drier part of the fin(s) to assist with the sealing process. After pour, the technician will mark the outside of the weir box at the location(s) where the original leak was. This incase further work may be required for a better seal. After the urethane is poured and let to cure (usually overnight) the job is inspected to determined seal effectiveness. In the event we still have some leakage; whether the following day or later, an additional procedure may be performed. If leaking, the weir box is fabricated out of 11ga galvanized sheet metal which is thick enough for completing a 1/16" NPT. The technician will decide where (usually where it's been marked) and how many 1/16" D&T’s (drill & taps) are required. Once additional d&t's are completed, injection valves installed, then a special 2-part sealant (must be approved from a dielectric and DGA standpoint) will be injected. The thought is: now that there is cured urethane above the original leak(s) and we have marked the weir box for injecting close to that spot, we have created a bridging barrier for our sealant to back up against (so as not to extrude out the top of the weir box).

Power Transformers Articles